Tozzi Sud operates mainly within EPC (Engineering, Procurement, and Construction) contracts, that is, taking full charge of the entire process, from the engineering, to the supply of materials, and construction until the Customer’s performance requirements are met.

The Customer has the advantage of supplying only the technical specifications describing the module requested, specifying the anticipated performance, the reference standards, and the contractual terms to be met.
Following these specifications, the complete detailed engineering is developed and gradually submitted to the Customer for approval.

The development of an EPC (Engineering, Procurement, and Construction) order takes place in accordance with the following scheme:

  • BID
  • Contract award
  • Kick off meeting KOM
  • Basic engineering
  • Detailed engineering
  • Main machinery and packages definition
  • Shop drawings
  • Purchase stage
  • Structural prefabrication
  • Structural assembly at yard
  • Painting and PFP (Passive Fire Protection) application
  • Roof / wall / floor Insulation
  • Equipment installation
  • HVAC duct & machinery installation
  • Piping prefabrication
  • Piping Installation
  • Electrical & instrumental installation
  • Electrical & Instrument interconnecting
  • Mechanical completion
  • Pre-commissioning
  • Commissioning
  • As built and final dossiers